Incentive Information
Before You Apply:
Before installing your new charging stations, follow these 3 steps:
- Consult the city of Alameda’s Electric Vehicle Supply Equipment (EVSE) Checklist and the California EV guidebook for permitting requirements and best practice suggestions
- Submit a completed EV charger information form to AMP for approval*
- Submit a completed permit application to the city of Alameda permit center**
*Send form to AMP by email or submit directly to the AMP engineering office at 2000 Grand Street. For questions, call the AMP engineering main line at 510-748-5676. AMP will verify local power availability prior to permit application.
** For more information about permitting, contact the city of Alameda permit center, open 7:30 a.m. – 3:30 p.m., M-Th, 2263 Santa Clara Ave. Room 190, (510) 747-6800
Terms and Conditions:
- Customer is solely responsible for installation of all rebated products to the manufacturer’s specifications.
- AMP reserves the right to reject any application that is incomplete or fails to meet the program requirements.
- Customer agrees that AMP reserves the right to inspect the installation premises of the charging stations for 24 months after the date of application or request additional documentation prior to rebate payment. The rebate may be revoked by AMP if this condition is not met by the customer.
- Alameda Municipal Power disclaims all liability, loss, or damage that may arise because of the applicant's participation in this program.
- AMP reserves the right to modify or discontinue this program without prior notice at its discretion.