Incentive Information
Before installing your new charging stations, follow these 3 steps:
- Consult the city of Alameda’s Non-Residential EV Permitting Checklist and the California EV guidebook for permitting requirements and best practice suggestions
- Submit a completed EV charger information form to AMP for approval*
- Submit a completed permit application to the city of Alameda permit center**
*Send form to AMP by
email or submit directly to the AMP engineering office at 2000 Grand Street. For questions, call the AMP engineering main line at 510-748-5676. AMP will verify local power availability prior to permit application.
** For more information about permitting, contact the city of Alameda
permit center, open 7:30 a.m. – 3:30 p.m., M-Th, 2263 Santa Clara Ave. Room 190, (510) 747-6800